Home | News | MARINE XII: INSTALLATIONS COMPLETED AND FULL PROJECT FILM NOW RELEASED

MARINE XII: INSTALLATIONS COMPLETED AND FULL PROJECT FILM NOW RELEASED

4 December 2025 Projects

In partnership with Wison New Energies, Geocean carried out the transport and installation of the FLNG mooring system off the coast of Pointe Noire, Republic of the Congo (33 m water depth).

The teams installed the driven anchor piles, the submerged Swivel & Yoke (SSY), and the flexible riser, performing all drilling, grouting, and subsea connection operations with high precision. The infrastructures are now fully installed and ready for the FLNG hook up.

Through this operation, Geocean ensures the stability and reliability of the FLNG Marine XII mooring system, directly contributing to the success of the country’s first floating liquefaction project.

 

Marine XII full project