Customer :
EDRA
Role :
Main Contractor
Key date :
2016-2017
Location :
Port Saïd - EGYPT - Egypt
Description of the Project
Power Plant Pipelines Replacement
Work done and added value of our solution
- Number of Lines: 6
- Trench Length: 130ml x 12m for the Intake Lines + 180ml x 15m for the Outfall Lines
- Total Pipeline Length:
Intake 2 x 115m
Outfall 2 x 160m
Chlorination line 2 x 145m
- Diameter: DN2500 for the Intake and Outfall Lines and DN200 for the Chlorination Lines
- Max Water Depth:-6m/MSL
- Pipe Specifications: HDPE Pipes PE100