La Pampilla, Lima, Peru : operations under progress

The Repsol Pampilla Refinery (RELAPASAA) awarded GEOCEAN to install a fourth terminal for the loading and unloading of refined products through an SPM system.

The offshore pipelines under progress will connect the PLEM to the onshore terminal.

  • Two Pipelines: Length: 4,119 m each – Diameter 18″
  • SPM facilities installed in 19m water depth.

The following operations have been completed:

  • Anchors and Chains of SPM system installed and tensioned
  • Mobilization of the YAGANA pipelay vessel
  • North Pipeline Beach pull, laying and Precommissioning (pigging/gauging + hydrotest)
  • South Pipeline Beach pull
  • Electrical cable Bundle pull
  • barge, YAGANA, monobuoy, anchor, pipeline, terminal, Peru