Hippocampe Project – EPPLN – Port-La-Nouvelle – Successfull Delivery

The new EPPLN sealine is now fully operational in Total Energies / Dyneff‘s Terminal in Port La Nouvelle!

GEOCEAN was awarded early 2021 a contract for the decommissioning of the existing pipeline and its substitution with a new petroleum products import line.
We have safely and successfully executed the whole EPCI project in a short amount of time, meeting all Client’s production milestones and thus minimizing the offshore offloading disruption to a few weeks only.

First tanker offloaded its products on the 4th of November 2021, and since then deliveries occur continuously every 10 days.
All removed pipeline sections were sent to qualified recycling facilities.

Congratulations to all GEOCEAN team and local partners who did a great job in delivering a high-quality project on time.