Le 08 September 2025

🎬 Wilhelmshaven FSRU Project: A successfully completed offshore challenge

We are proud to share the recap video of our contribution to the floating LNG terminal (FSRU) in Wilhelmshaven. This project realised in collaboration with ECOnnect involved installing the jettyless IQuay infrastructure and pipelines connecting the FSRU Excelsior directly to the German grid.This strategic project has enabled Germany to secure and diversify its liquefied natural gas (LNG) supply, highlighting the...

News

Le 15 July 2025

Marine XII project: Installation of the Yoke and Riser

An anchoring system specific to gas transport The gas anchoring and supply system plays a central role in floating liquefied natural gas (FLNG) operation. A floating tank for natural gas, transported from the production platforms and then transferred to a transport vessel. The latter moors alongside the FLNG to load and transport the LNG to a terminal. This infrastructure provides a mooring...

Projects

Le 10 June 2025

Arrival of the HLV on site: A new milestone in installing the mooring system

The HLV’s role: from logistics to installation The HLV made a first stop at Pointe-Noire, where she was reconfigured from transit to installation mode. Crews performed final inspections, fine-tuning, and preparations to guarantee flawless emplacement of the cargo. Aboard, several essential components were carefully repositioned to facilitate their offshore installation: The Yoke, ultimate element of the mooring system, is destined to be...

Projects

Le 20 May 2025

Marine XII project in Congo: Installation of anchor piles

Positioning of the barge Before drilling operations can begin, the Jack-Up Barge (JUB) is positioned on site and raised above sea level using its legs resting on the seabed. This positioning is essential to ensure optimal conditions for the following drilling operations.     Installation of the casing, the drilling guide The casing, a metal guide tube, is installed to ensure accurate drilling: Positioning of the...

Projects

Le 11 March 2025

Launch of operations for the Marine XII project in the Congo: A look back at the preparations and mobilisation at sea

Summary of preparations at Pointe-Noire Over the past few weeks, we have mobilised and assembled all the necessary equipment at the port of Pointe-Noire. The drilling and cementing units have been prepared and assembled on site, thus guaranteeing a reliable and ready-to-use configuration. The diving spread, including a decompression chamber, a control cabin, and two diving lifts (LARS), is already mobilised...